Solar farm finance in the UK: what a ground-mount project costs, earns and borrows
Reviewed by the Commercial Solar Finance editorial team — independent advisers (we take no installer or lender commissions). Last reviewed: 14 October 2026.
Solar farm finance is project finance: a special-purpose company owns the site, a lender advances senior debt against contracted revenue, and the developer or landowner holds the equity. This guide gives the sourced numbers behind that structure — what a UK solar farm costs to build and run, what its output sells for, what the land is worth, and what planning and grid rules apply — so that a landowner, developer or investor can read a funding proposal with the right figures in hand.
Arup for DESNZ (final report 14 July 2025, 2023 prices, solar above 5 MWp): total capex £526 (low), £659 (central) and £788 (high) per kWp, of which grid connection and substation is about 18%.
Contracts for Difference allocation round 7a (results 10 February 2026): solar PV above 5 MW cleared at £65.23 per MWh in 2024 prices — 157 projects, 4,905 MW, delivery 2027–28 and 2028–29.
What a solar farm costs to build and run
The reference cost set for UK ground-mount solar is Arup's 2024 assessment for DESNZ, published in final form on 14 July 2025, for projects above 5 MWp in 2023 prices (sample 11 to 225 MWp, median 52 MWp). Its central case is a total of £659 per kWp installed; the low and high cases bracket £526 and £788.
| Cost line (per kWp, 2023 prices) | Low | Central | High | Note |
|---|---|---|---|---|
| Pre-development (planning, surveys, design) | £12 | £24 | £59 | Spent before a lender is involved; at risk |
| Construction (modules, mounting, inverters, civils) | £423 | £522 | £601 | The EPC contract |
| Infrastructure (grid connection, substation) | £91 | £112 | £129 | About 18% of capex; the line most sensitive to location |
| Total capex | £526 | £659 | £788 | Arup for DESNZ, Table 41 |
| Operating cost (per MWp per year) | £6,500 | £9,300 | £12,300 | O&M, insurance, connection and use-of-system; excludes land rent, business rates and community benefit |
| Net load factor | 11.5% | 12.2% | 14.5% | Roughly 1,070 kWh per kWp in year one at the central case |
| Degradation and life | 0.29%/yr; 35 yrs | 0.30%/yr; 38 yrs | 0.45%/yr; 40 yrs | Drives the tail of the revenue model |
Land take is about six acres per megawatt for existing projects (Solar Energy UK's figure, cited by Carbon Brief on 25 August 2022), so a 5 MWp site needs roughly 30 acres and a 50 MWp site around 300.
Where the revenue comes from
| Route | What it pays | Who can use it | Finance view |
|---|---|---|---|
| Contracts for Difference | A government-backed strike price: AR7a solar cleared at £65.23/MWh (2024 prices) | Solar above 5 MW only, through the allocation rounds | The most bankable revenue; lenders size most of the senior debt on it |
| Corporate PPA | A bilateral fixed price or a discount to market for 10–15 years | Any size with a creditworthy buyer | Bankable in proportion to the buyer's credit and the term |
| Merchant sale | The wholesale market price, hour by hour | Any size | Lenders haircut it heavily; usually the equity's upside, not the debt's security |
| Smart Export Guarantee | A supplier-set export tariff | Installations up to 5 MW only | Relevant to a farm-scale array, not a solar farm |
| Renewable certificates (REGOs) | Sold with or separately from the power; no official price | Any accredited station | A secondary line; sell them and the buyer gets the renewable claim |
Two historic routes are closed: the Renewables Obligation closed to new capacity on 31 March 2017 (existing ROCs run for 20 years), and the Feed-in Tariff closed to new applicants on 1 April 2019. A new project has the four live routes above.
Land: lease or own
Most UK solar farms are built on leased land. The published benchmarks are dated and should be treated as such: subsidy-free solar rents “anywhere between £850 and £1,100 per acre per annum” with revenue top-ups of around 4–6% of developer revenue (Stephens Scown, published December 2021, reviewed September 2023), and rents “in excess of £800 an acre, and can be £1,000” with a revenue share at least matching the base rent (Farmers Weekly business clinic, June 2020). Leases run 30 to 50 years, options typically require construction within one to three years, and a co-located battery usually adds rent per megawatt. For the landowner the lease is income; for the developer it is an operating cost that sits outside the Arup opex figures above.
How the debt is sized and what the equity carries
A lender to a solar-farm SPV advances senior debt against the revenue it can rely on: a CfD or a long-dated corporate PPA counts in full, a merchant tail is discounted, and the loan is sized so that forecast cash after operating costs covers debt service with a margin the bank sets. Pre-development spend, planning risk and the grid connection deposit are carried by the equity until consent and a connection offer are in hand; construction is then funded by the debt and equity together against the EPC contract, and the loan converts to a term facility at commissioning. Interest is priced off Bank Rate (3.75% on 16 September 2026) or SONIA plus a project margin.
Tax follows the same rules as a rooftop array: the plant is special-rate expenditure, so a company claims the Annual Investment Allowance on the first £1m and the 50% first-year allowance above it (see the capital allowances guide); in England the generation and storage plant is excluded from the rating valuation until 31 March 2035 while the land itself remains rateable (see business rates and solar panels); and the output is a standard-rated supply of electricity for VAT.
Planning and grid
- A ground-mount scheme needs full planning permission. Under the Development Management Procedure Order 2015 the determination period is 13 weeks for a major application (a site of one hectare or more) and 8 weeks otherwise; the real timetable is set by surveys and consultation, not the statutory clock.
- From 31 December 2025 the Nationally Significant Infrastructure Project threshold for solar in England is 100 MW (SI 2025/694), up from 50 MW; schemes above it go through the development consent process rather than the local authority.
- The grid connection is the longest lead item and the second-largest cost line. A connection offer with a firm date is a condition of every lender's credit approval; the offer, not the planning consent, usually sets the financial close date.
Worked illustration: a 5 MWp site on 30 acres (modelled, not a client engagement)
At the Arup central case a 5 MWp solar farm costs about £3.3m to build (£2.6m to £3.9m across the low and high cases). Year-one output at the central load factor is roughly 5,350 MWh. Priced at the AR7a clearing level of £65.23 per MWh — a 5 MWp site sits below the CfD threshold, so in practice this is a PPA price in line with it — revenue is about £349,000. Operating costs at £9,300 per MWp come to £46,500 and rent on 30 acres at £1,000 an acre to £30,000, leaving an operating surplus of roughly £272,000 before finance, tax and degradation: about 8.3% of the central capex, 10.4% at the low case and 6.9% at the high. That is the number a lender sizes debt against and an equity investor compares with the alternatives; the price assumption and the land cost are the two inputs that move it most.
Assumptions are stated so that each can be replaced. For an estate weighing a solar farm against rooftop arrays on its buildings, the six rooftop financing routes and the agricultural solar finance guide cover the smaller end.
Claims table: every figure on this page and its source
Every number and proper noun above is listed here with where it comes from and the date it was checked. If a row is not here, the figure should not be on the page.
| Claim | Source | Checked |
|---|---|---|
| Capex £526/659/788 per kWp; opex £6.5/9.3/12.3k per MWp/yr; load factor 12.2% (11.5–14.5%); degradation 0.29/0.30/0.45%/yr; life 35/38/40 yrs; sample 11–225 MWp | Arup for DESNZ, Renewable Energy Generation Cost and Technical Assumptions 2024, final 14 July 2025, Table 41 (2023 prices) | 14 October 2026 |
| About six acres per megawatt for existing projects | Solar Energy UK, cited in Carbon Brief factcheck, 25 August 2022 | 14 October 2026 |
| CfD AR7a solar PV >5 MW: £65.23/MWh (2024 prices), 157 projects, 4,905 MW, delivery 2027/28 and 2028/29 | DESNZ allocation round 7a results, 10 February 2026 | 14 October 2026 |
| Rents £850–£1,100 per acre per annum; revenue top-ups 4–6%; leases 30–50 years | Stephens Scown (published 3 December 2021, reviewed 27 September 2023) | 14 October 2026 |
| Rents in excess of £800 and up to £1,000 per acre; revenue share at least the base rent; developers seek 35-year-plus leases | Farmers Weekly business clinic, 1 June 2020 (Carter Jonas) | 14 October 2026 |
| DMPO 2015: 13 weeks for major applications (site of 1 ha or more), 8 weeks otherwise | Town and Country Planning (Development Management Procedure) (England) Order 2015, arts 2 and 34 | 14 October 2026 |
| Solar NSIP threshold 100 MW in England from 31 December 2025 | SI 2025/694 (made 9 June 2025) | 14 October 2026 |
| RO closed to new capacity 31 March 2017; FIT closed to new applicants 1 April 2019 | Ofgem | 14 October 2026 |
| Bank Rate 3.75% (held 17 September 2026; next decision 5 November 2026) | Bank of England | 14 October 2026 |
| England rates exclusion for renewables plant to 31 March 2035 | SI 2022/405 | 16 September 2026 |
Frequently asked questions
How much does a solar farm cost to build in the UK?
How much land does a solar farm need?
What does a solar farm earn per MWh?
How much rent does a solar farm pay a landowner?
Does a solar farm need planning permission?
Finance route checker
Which finance route fits your solar project?
Answer six questions and see an indicative shortlist straight away: cash purchase, hire purchase, loan, lease or PPA, ranked for your tax position, premises and budget. If you want a reply, send your answers to us by email at the end.
Thanks, your answers are with us.
We reply by email. Your shortlist stays on this page.
Something went wrong.
The form could not be submitted. Please try again, or email info@commercialsolarfinance.co.uk directly.
Run the numbers on your project
Build the after-tax model with the right reliefs applied — no missed deductions, no double-counted benefits.
Request a finance review