FYA deadline calendar — month-by-month planning
A working calendar for capturing the 50% First Year Allowance before the 31 March 2026 deadline. Month-by-month order placement guidance by project size, expected lead times, and what to do if you miss the window.
Lead-time assumptions: 12–48 weeks from contract execution to commissioning depending on project size, with DNO process and procurement as the primary constraints. Verify against your specific site before committing to commissioning timing.
The deadline mechanics
The 50% First Year Allowance applies to qualifying capital expenditure on commercial solar PV incurred before 31 March 2026 (unless extended in a future Budget). For capital allowance purposes, expenditure is "incurred" on the date the asset is brought into use — typically when commissioned and producing electricity, evidenced by G99 commissioning and meter records.
For a project to capture FYA, commissioning must complete by 31 March 2026 (or by your accounting year-end if it falls before that date). Working backwards through the typical lead times tells you when orders need to be placed.
Month-by-month planning calendar
May 2025
305 days to deadlineAll sizes — comfortable timing on most projects
- Begin discovery and design for projects targeting end-March 2026 commissioning.
- Order placement before end-Q3 2025 safe for 100kW–1MW projects.
- DNO process can begin in parallel for larger projects.
June 2025
274 days to deadlineAll sizes
- Comfortable timing — full design and DNO process feasible.
- Order placement Q3 still on track for end-March 2026 commissioning.
July 2025
244 days to deadlineAll sizes — last comfortable window for 1MW+
- 1 MW+ projects need orders placed by end-July to safely commission by end-March 2026.
- DNO connection studies for larger projects must be in progress.
August 2025
213 days to deadlineBelow 500 kWp — comfortable; above 500 kWp — tight
- 1 MW+ projects: order placement now is at the limit. Rapid progression required from here.
- 500 kWp projects: order by end-August for comfortable timing.
- 100–250 kWp: still substantial slack.
September 2025
183 days to deadlineBelow 500 kWp; 1MW+ now risky
- 1 MW+ projects: order placement now produces tight DNO + procurement + construction sequence. Consider deferring rather than accepting risk.
- 500 kWp: comfortable for now.
- Discovery work for end-2025 / early-2026 year-ends should kick off if not already in progress.
October 2025
152 days to deadline300–500 kWp; below 300 kWp comfortable
- 500 kWp+ projects need order placement now to safely commission by end-March 2026.
- 300 kWp: still feasible with smart sequencing.
- Below 300 kWp: comfortable.
November 2025
122 days to deadlineBelow 300 kWp
- Last reliable window for 300 kWp projects — order now to commission by end-March 2026.
- Below 200 kWp: comfortable timing.
- Above 300 kWp: defer to post-deadline scenario unless DNO position is already established.
December 2025
92 days to deadlineBelow 200 kWp
- 200 kWp projects feasible only with established DNO position and pre-procured equipment.
- Below 100 kWp: realistic for end-March commissioning.
- Above 200 kWp: post-deadline timing now realistic — model both FYA and post-FYA cases.
January 2026
60 days to deadlineBelow 100 kWp
- 100 kWp+ projects: post-deadline timing now expected. Recommend deferring for clean post-deadline launch with predictable timing.
- Sub-50 kWp: realistic with simple installation.
February 2026
30 days to deadlineSub-50 kWp only
- Only sub-50 kWp simple installations realistic for end-March 2026 capture.
- Above 50 kWp: clean defer to post-deadline. The post-deadline IRR is still 12–15% on profitable trading companies.
March 2026
1 days to deadlineCliff-edge — only commissioned-by-31-March projects qualify
- No new orders capture FYA — equipment must be commissioned and producing electricity by 31 March 2026.
- Final commissioning push on projects already in late-stage construction.
April 2026 onwards
0 days to deadlinePost-deadline — special-rate pool only
- No FYA available. All qualifying capex enters special-rate pool at 6% writing-down allowance.
- Lifetime tax value drops from 17–19% of capex (FYA route) to ~9% (special-rate pool only).
- Project IRR drops by 2–3 percentage points but most projects still attractive on profitable trading companies.
- Re-engage if FYA extended in subsequent Budget; otherwise plan around AIA where headroom available.
Lead-time breakdown
Total project lead time varies 20–48 weeks depending on size. The components:
- Discovery and design: 4–8 weeks (site survey, structural review, demand modelling, financial structuring). Add 4 weeks for finance package execution.
- DNO process: 6–24 weeks depending on system size. Above 200 kWp triggers G99 connection studies; above 500 kWp often triggers reinforcement studies adding further weeks. DNO can become the binding constraint; don't assume parallel processing.
- Procurement: 8–14 weeks for modules and inverters from order to delivery. Tier-1 module suppliers typically 10 weeks; central inverter manufacturers can run 14 weeks.
- Construction: 1–6 weeks depending on system size and access complexity. Larger projects sequence across multiple roof sections.
- Commissioning: 1–4 weeks. G99 commissioning requires DNO inspection slot — can take 2–6 weeks to schedule on busy DNO patches.
Recommended actions by accounting year-end
| Year-end | FYA Window | Recommended action |
|---|---|---|
| Before 30 Sep 2025 | Already missed for current year; available for following year | Plan toward the next financial year capturing FYA in early-2026 commissioning |
| Oct–Dec 2025 | Full window — orders placed by July 2025 safely capture FYA | Push completion now if not already in motion. Above 500 kWp: order by August 2025 latest |
| Jan–Mar 2026 | Tight window — orders placed by Sep 2025 most reliable | Prioritise smaller projects (sub-300 kWp). Larger projects: model post-FYA case as fallback |
| After 31 Mar 2026 | Post-deadline — special-rate pool only | Plan around AIA where headroom available; otherwise accept ~9% lifetime tax saving via SRP |
FYA planning FAQs
When does HMRC consider expenditure "incurred" for FYA purposes?
What if we miss the 31 March 2026 deadline?
Could the FYA be extended in the Budget?
Should we accept higher project risk to capture FYA?
Can AIA fill the gap if we miss FYA?
Map your accounting year-end against project timing
Our advisory engagement maps year-end FYA capture timing against your specific project size, demand profile, and DNO position. We model both FYA-capture and post-deadline scenarios so you can make an informed timing decision.
Request a finance review