G99 connections for UK commercial solar — 2026 guide
G99 is the engineering recommendation governing connection of distributed generation (including commercial solar above 50 kW peak) to the UK electricity distribution network. Above 50 kW, G99 application to your local DNO is mandatory. Above 200 kW, full network impact assessment is typical. Above 500 kW, network reinforcement studies often trigger. Each threshold adds time, cost, and complexity to project delivery.
When G99 applies
Connection of distributed generation to the UK electricity distribution network is governed by Engineering Recommendation G99. The thresholds:
- Below 16 A per phase (3.68 kW) — G99 not required; connection under G98.
- 16 A to 32 A per phase (3.68-7.36 kW) — G99 Notify-Only. Inform DNO; no detailed application.
- 32 A to 50 kW — G99 Type Tested Connect. Standard application; typically 6-8 weeks DNO process.
- 50 kW to 1 MW — G99 Type A application. Standard process with assessment of network impact. 8-16 weeks typical DNO process.
- 1 MW+ — G99 Type B/C/D application. Detailed network impact assessment, often reinforcement requirements. 16-40 weeks typical DNO process.
Typical DNO process timeline
For a typical 200-500 kW commercial solar G99 application:
Application submission (week 0)
Submit G99 application to your local DNO via their online portal. Include site details, system specifications, and electrical infrastructure information.
Application accepted (week 1-2)
DNO confirms application is complete and assigns it to the network connections team.
Network impact assessment (week 2-8)
DNO assesses local network capacity, voltage profile, and ability to accept the proposed export. May require additional protection settings, AVR studies, or fault level assessment.
Connection offer (week 8-12)
DNO issues connection offer specifying conditions, costs, and any required network reinforcement. Offer typically valid for 90 days.
Acceptance and payment (week 12-16)
Customer accepts offer and pays connection charges. Reinforcement work scheduled if required.
Network reinforcement (if required, week 16-32)
DNO undertakes reinforcement work — transformer upgrade, cable upsizing, or substation modifications. Adds 12-20 weeks to project timeline.
Commissioning inspection (week 32+)
DNO inspector witnesses commissioning, verifies protection settings, and grants final connection consent.
Common reinforcement triggers
Network reinforcement adds material cost (£15k-£200k+) and time (3-9 months) to projects. Common triggers:
- Voltage step — large generation can cause voltage rise on the network. Reinforcement may be required to maintain voltage within statutory limits.
- Reverse power flow — older transformers and protection systems may not accommodate reverse power flow. Replacement or modification required.
- Fault level — adding generation increases prospective fault current at downstream connections. Switchgear upgrades may be required.
- Network capacity — local cables or transformers may be at capacity. Upsizing required for new generation.
- Protection coordination — protection settings need to be compatible with new generation. AVR (Automatic Voltage Regulator) studies often required.
Technical FAQs
Can I install commercial solar without G99 if I don't export?
How much does a G99 application cost?
Can I avoid network reinforcement charges?
How does G99 differ between DNOs?
What if my G99 application is rejected?
Related guides
Need this assessed for your specific site?
Send postcode, building details, and electricity supply information. We'll come back inside five working days with a project-specific assessment alongside the finance modelling.
Request a finance review