Public sector

PSDS Phase 4: the three patterns in funded applications

Update, 10 September 2026: PSDS Phase 4 closed to applications in November 2024 and DESNZ now describes it as the scheme's final phase. This article is kept as a record of how Phase 4 bids were assessed; for the current position and the routes open to public bodies now, see public sector solar funding in 2026.

Published 2026-02-26 · 9 minute read · By Commercial Solar Finance editorial team

PSDS Phase 4 closed in November 2024 after a short window. Three patterns separate winning applications from losing ones, and they have less to do with technology choice than with how the business case is framed.

The PSDS Phase 4 application window ran from 9 October to 25 November 2024, and the scheme announces no further round. The same three patterns separated funded applications from unsuccessful ones as in Phase 3 — and they had less to do with technology choice than with how the business case was framed.

The cost-per-tonne metric is everything

PSDS scoring was dominated by cost-per-tonne-of-CO₂-saved over the project lifetime. Solar-only applications struggled there because, on a per-tonne basis, solar is one of the more expensive decarbonisation options for an organisation already operating on partly-decarbonised grid electricity. A 2026 marginal grid carbon factor of 0.18 kg CO₂/kWh means that even a high-yielding solar project saves only ~180 tonnes per MWp per year — and per pound of capex that is a smaller carbon saving than measures that replace gas heating.

Bundled applications won. A solar + heat pump + fabric efficiency package on the same site delivered better cost-per-tonne because heat pumps replaced direct gas use (CO₂ factor ~0.21 kg/kWh), where the savings per pound spent were stronger.

What worked in Phase 4

Bundle structure. Successful applications generally included solar PV + air-source heat pumps + LED relighting + BMS + roof insulation as a single package, with the heat pump driving the cost-per-tonne metric and solar offsetting the heat pump's grid load. Solar standalone applications won only on sites where the heat is already decarbonised (electric heating in a school, for instance).

Real demand modelling. Applications that referenced half-hourly demand profiles, not annualised consumption, made a stronger case because the assessor could verify self-consumption assumptions.

Specific carbon counterfactual. The strongest applications nominated a specific grid emissions factor with a year-by-year decarbonisation trajectory drawn from the National Grid FES Net Zero scenario, rather than a flat assumption. This shifts the lifetime CO₂ savings calculation noticeably.

Maintenance and end-of-life. Applications that costed 25 years of operation and maintenance, not just installation, made a stronger case.

What weakened a bid

Cost per tonne above the threshold. Phase 4 assessed the carbon cost of each bid against a threshold set in its guidance. Solar-only projects struggled to clear it without unusual local circumstances (e.g. very high tariffs, very large sites with constrained grid alternatives).

Insufficient client-side capability. Applications from bodies with no clear delivery resource made a weaker case; a named project sponsor, internal procurement capacity and a credible plan from engagement to completion made a stronger one.

Generic technical specification. Boilerplate solar specifications without site-specific structural and DNO assessment made a weak case; applicants were expected to show evidence of site survey work.

What it meant for public-sector planning

For schools, NHS trusts and local authorities, the Phase 4 pattern was: lead with heat decarbonisation, anchor on cost per tonne, and treat solar as the complementary measure rather than the headline. Where heat was already electric, solar could lead; in a building with significant gas heat use, the heat pump was what won the bid. Portfolio bids also helped, because one package across several sites spread the overhead. Phase 4 has closed, so this is a record of how bids were judged, not a route open today.

Timeline

The Phase 4 application window ran from 9 October to 25 November 2024. It is closed, no further round has been announced, and in June 2025 the government said it would fund no projects beyond those already awarded (Salix, 12 June 2025).

Frequently asked questions

Will there be another PSDS phase?
No new phase is planned. PSDS Phase 4 closed to new applications in November 2024, and in June 2025 the government said it would fund no projects beyond those already awarded.
What did a strong PSDS Phase 4 application look like?
Strong applications scored well on: (1) low £/tCO2 cost-per-tonne of abatement; (2) a multi-site portfolio that dilutes the cost of complex buildings; (3) verified baseline energy consumption data (AMR or HH metered); (4) a technically credible contractor with public sector delivery experience; (5) a phased delivery plan that demonstrates risk management. Applications citing heat pump installation with solar PV supporting grid load typically score better than solar-only projects because the combined measure achieves greater CO2 reduction per £.
What caused PSDS applications to be rejected?
The most common rejection reasons in Phase 3 applications were: cost-per-tonne above the informal £250/tCO2 threshold; unverified baseline consumption data (relying on estimates rather than meter data); design specifications provided by a single contractor without competitive procurement evidence; and single-site applications where one difficult building dominates the cost. Public sector bodies without a Net Zero estate strategy on record also scored lower, even where the technical measures were sound.
Could solar PV alone qualify for PSDS funding?
Solar PV alone could qualify, but it was less competitive than bundled heat-and-power packages. The CO2 abatement from solar is calculated using the grid carbon intensity factor — at 0.233 kgCO2/kWh in 2026, a 100kWp system generating 90,000 kWh/year abates roughly 21 tCO2/year. At £120,000 installed cost, that is £286/tCO2 over 20 years — marginal for PSDS. Pairing solar with heat pump conversion, which removes gas consumption at much higher CO2 rates (0.183 kgCO2/kWh gas), dramatically lowers the blended cost-per-tonne.

Finance route checker

Which finance route fits your solar project?

Answer six questions and see an indicative shortlist straight away: cash purchase, hire purchase, loan, lease or PPA, ranked for your tax position, premises and budget. If you want a reply, send your answers to us by email at the end.

Email me this shortlist

Send your answers to us and we reply by email. We do not pass your details to installers or lenders without your permission.

Your answers and contact details are used to reply to this enquiry. See our privacy notice.

Need this analysis applied to your specific project?

Send postcode, half-hourly data file, and accounting year-end. We reply by email.

Request a finance review