Public sector · NHS · PSDS

NHS Trust PSDS Phase 4 application strategy: a retrospective

Update, 10 September 2026: Phase 4 was the final PSDS phase and closed to applications in November 2024, so no new bids can be made. The bundling logic below still applies to any successor scheme; for what NHS trusts can do now, see our guide to public sector solar funding routes.

Published 2026-04-22 · 10 minute read · By Commercial Solar Finance editorial team See our East Midlands NHS Trust PSDS case study for a worked example of a successful bundled portfolio application.

In PSDS Phase 4, NHS trust bids that bundled solar with heat pumps and fabric efficiency across a multi-site estate did better on cost per tonne, and portfolio bids outscored single-site bids. PSDS closed to new applications in November 2024; this retrospective records what worked.

PSDS Phase 4 was the final round. PSDS closed to new applications in November 2024 and Phase 4 is its final phase. In that round, the patterns that separated funded Trust bids from unsuccessful ones had less to do with technology choice than with how the bid was framed and what scope it covered. This is a record of those patterns: the scheme is closed.

The cost-per-tonne metric is everything

PSDS assessed bids on the cost of the carbon saved over the project lifetime, against a carbon cost threshold set in each phase's guidance; the scheme closed to new applications in November 2024. Solar-only NHS Trust applications struggled here because hospital electricity demand was partly already decarbonised on the grid — solar offset grid imports that average ~0.18 kg CO₂/kWh, so solar alone saves less carbon per pound than measures that replace gas heating.

Bundled applications won. Heat pump installations replaced direct gas heating (CO₂ factor ~0.21 kg/kWh), where carbon savings per pound spent were stronger. Solar combined with heat pumps and fabric efficiency therefore scored better on the carbon cost test.

The multi-site portfolio approach

Portfolio-level bids had advantages that single-site bids did not. A Trust bid could combine several estate sites:

  • Acute hospital — large continuous-load site, strong solar self-consumption, partial heat-pump opportunity
  • Community hospitals — typically 2–6 per Trust, smaller scale, heat-pump opportunity often substantial (gas-heated buildings)
  • Ambulance HQ + ambulance stations — operational estate with day-and-night demand profiles
  • Mental health units — variable demand, strong fabric and BMS opportunities
  • Corporate offices and admin sites — daytime demand, easier solar deployment

Why portfolio bids did better: the cost-per-tonne metric averaged across the bundle, so sites with strong economics (community hospitals with heat-pump bundles) pulled down the average. Single-site bids were evaluated alone.

The bundled-package recipe

Funded Phase 4 NHS bids typically combined four interventions:

  1. Air-source heat pumps on community hospital and gas-heated estate

    Highest cost-per-tonne benefit. Replaces gas heating with electricity-driven heat. Combined with solar PV creates substantial Scope 2 reduction.

  2. Solar PV across acute hospital and rooftop-suitable estate

    Provides electricity for heat pumps and broader site demand. Strong continuous self-consumption on 24/7 hospital sites.

  3. LED relighting across the entire estate

    Smaller individual saving but very low cost-per-tonne. Lifts the bundled metric.

  4. Building management system upgrades

    Optimises heat pump and solar performance. Provides demand-management capability for winter peak periods.

Phase 4 timeline

The Phase 4 application window ran from 9 October to 25 November 2024. It is closed, no further round has been announced, and in June 2025 the government said it would fund no projects beyond those already awarded (Salix, 12 June 2025).

What weakened a bid

Solar-only bids struggled on cost per tonne, and bids that relied on annual consumption rather than half-hourly demand modelling, or that named no delivery resource and had no credible plan from engagement to completion, made a weaker case. None of this applies to a new bid, because the scheme has closed.

What Trusts can do now

PSDS is closed, so there is no bid to prepare. For the routes open to public bodies now, see public sector solar funding in 2026.

Frequently asked questions

What was PSDS Phase 4, and is it still open?
PSDS Phase 4 was the final round of the DESNZ grant programme for heat decarbonisation and energy efficiency in public sector buildings. It closed to new applications in November 2024, and in June 2025 the government said it would fund no projects beyond those already awarded. NHS Trusts, Local Authorities, blue-light services and schools were the main eligible body types, and solar PV was eligible where it supported a heat decarbonisation package or reduced grid dependency for electric heat pumps.
How was cost per tonne of CO2 calculated for a PSDS bid?
DESNZ assessed PSDS bids primarily on £/tCO2 abated over the project lifetime. For solar PV the calculation took lifetime generation (25 years × annual yield in kWh), applied a grid carbon intensity factor, and divided total project cost by total tonnes abated. For example, at ~0.233 kgCO2/kWh a 200kWp system generating 180,000 kWh/year abates around 1,050 tCO2 over 25 years; at £200,000 installed cost that is £190/tCO2.
Did bundling several sites help a PSDS bid?
Yes, bundling generally helped. Bundled bids achieved a lower average £/tCO2 by including high-impact, low-cost sites alongside more complex ones, while single-site bids on difficult buildings often exceeded cost-per-tonne thresholds. The practical challenge was procurement: bundled projects needed a single contractor or a pre-agreed consortium to deliver across several sites.
What grant sizes did NHS trusts get under PSDS?
NHS Trust PSDS grants for solar-inclusive projects have ranged from £500k to over £10m depending on scope. Pure solar-only projects rarely secured the largest grants — the highest grant values went to integrated heat-and-power packages where solar reduces grid load for heat pumps. A 500kWp solar portfolio across five Trust sites could have attracted a £600k–£900k grant (covering 40–60% of capital cost) when bundled with LED and controls upgrades that improve the overall cost-per-tonne metric.

Finance route checker

Which finance route fits your solar project?

Answer six questions and see an indicative shortlist straight away: cash purchase, hire purchase, loan, lease or PPA, ranked for your tax position, premises and budget. If you want a reply, send your answers to us by email at the end.

Email me this shortlist

Send your answers to us and we reply by email. We do not pass your details to installers or lenders without your permission.

Your answers and contact details are used to reply to this enquiry. See our privacy notice.

Need this analysis applied to your specific project?

Send postcode, half-hourly data file, and accounting year-end. We reply by email.

Request a finance review